3 Installation
IC Equipment Thin-Layer cell
■■■■■■■■
9
3
Connect the cell output
Use a pressure screw (6.2744.014) to fasten a 1–1.5 m long piece of
the PEEK capillary (6.1831.010) to the Out connector on the measur-
ing cell.
Note
This capillary must be tested with the IC instrument the first time
the detector is put into operation, see Chapter "Start-up" in the
manual for the detector.
If the preheating capillary is not used, proceed as follows:
Connecting capillaries to the measuring cell
1
Connect the cell input
Use a pressure screw (6.2744.014) to fasten the detector input capil-
lary to the In connector on the measuring cell.
2
Connect the cell output
Use a pressure screw (6.2744.014) to fasten a 1–1.5 m long piece of
the PEEK capillary (6.1831.010) to the Out connector on the measur-
ing cell.
Note
This capillary must be tested with the IC instrument the first time
the detector is put into operation, see Chapter "Start-up" in the
manual for the detector.